ATLAS Level-1 Calorimeter Trigger Hardware Progress Meeting - 04 May 1999 Minutes Present: Tony Gillman, Bob Hatley, Viraj Perera, Richard Staley 1. ACTION list from previous meeting (20-4-1999): a) Richard has almost completed the write-up of the backplane transmission tests, which may be produced as an ATLAS note. (He has also succeeded in getting the GTL system to work at 160 Mbit/s (previously limited to 80 Mbit/s, with poor eye-patterns), by running the devices at 3.0 V and terminating the driven lines with 25 ohms instead of 50 ohms.) b) Some progress has been made towards resolving the outstanding issues relating to the ROD prototype specifications, and further discussions between Norman, Tony and Viraj will be arranged. c) The proposed workplan for the CCM prototype programme is still awaited from Tony and Viraj. 2. DSS system: a) DSS motherboard design/layout status Viraj reported that the schematics were finally completed and sent to the Drawing Office on 28th April 1999. In Darren's absence, Kevin has started component placement. He has found that the current FPGA package sizes will not permit the S-link connector to be mounted on the same side of the board, so it will be mounted on the other face, thereby adding one extra width unit to the module. (Of course, for non-S-link uses this connector need not be mounted.) It may also be possible at a much later stage to re-layout the board to allow the S-link connector to be mounted alongside smaller FPGAs, if considered useful. Bob pointed out that we must not overlook the potential cooling problems with closely- packed, dense double-sided boards in this system. Tony requested Viraj to obtain a breakdown of the projected layout time for this board from Chris Day. ACTION: Obtain breakdown of mother-board layout time from Drawing Office - Viraj b) LVDS daughter-cards status Richard reported that both these cards had been sent for manufacture during the previous week (w/b 26th April 1999). Five pcbs will be made, four of which will be assembled. All components are available or on order, with only the Berg 2mm connectors on long delivery (as already noted). While waiting for manufacture and assembly he will prepare a simple test jig to allow basic card functions (power, clocks, etc.) to be tested before the DSS motherboards are available for full testing. c) G-link daughter-cards status Bob reported that the Rx card was sent for manufacture also during the w/b 26th April 1999. Four pcbs will be made, two of which will be assembled. Bob has arranged for eight 2m SMR cable assemblies to be manufactured. It was decided that adapting Richard's simple test jig for basic tests would prove too difficult. For the Tx card, component placement is almost complete but no tracking has yet been started. As Darren will now switch to the high-priority DSS motherboard layout, further progress must await its completion. 3. ASIC designs: a) Serialising ASIC or Serialising FPGA? Viraj had no further information from Ian on his ongoing simulation studies with the Xilinx VIRTEX FPGAs. As reported at last week's Group Meeting, he currently appears to hit a speed limit of ~131 MHz, but expects this to increase significantly with further optimisation. The crucial question is whether the speed can reach (and exceed by a comfortable margin) 160 MHz. In addition, it was noted that further work is needed to implement all the functions resulting from the BC-demux scheme. b) CP ASIC status and schedule There was some discussion about how much work was needed to complete a first draft of the specifications for this device. Viraj has already written some parts of the document (including all the chapter headings), and it was felt that other people could usefully contribute, in particular to the sections detailing the algorithms. Physicist effort to define the algorithms in pseudo-code would be especially valuable in this area. It was again remarked that a C-to-VHDL translator could prove to be a very important tool for the actual design process. ACTION: Produce an estimate of the likely timescale for completing the design specifications - Viraj 4. CCM prototype: a) Review plans Tony proposed that Draft 4.0 of the design specifications should now be put up on the Web and the reviewers invited to begin assessing it. They should aim to spend the next two weeks or so going through it in detail, with a view to completing (?) the review process by early-June. 5. CPM prototype: a) Update Richard will dust off the draft document that he wrote many weeks ago and get it into a form which we can start discussing informally. ACTION: Prepare Draft 0 of the CPM prototype specifications document - Richard 6. Any other business: Tony mentioned that he had responded to a recent request from CERN for an estimate of our total pcb requirements. Apparently there is a potential safety issue regarding materials containing bromine, which involves normal printed circuit boards. All subsystems are invited to estimate their expected "hectareage" of such materials - ours would appear to be around 70 m2. * Next meeting - Tuesday 11th May at 11.00 - CR01, R1 at RAL. Tony Gillman