ATLAS Level-1 Calorimeter Trigger Hardware Progress Meeting - 13 April 1999 Minutes Present: Eric Eisenhandler, Norman Gee, Tony Gillman, Bob Hatley, Viraj Perera, Richard Staley 1. ACTION list from previous meeting (31-3-1999): a) Richard has almost completed writing up the results of the backplane transmission tests but wants to do some further measurements with the CMOS system at reduced supply voltages. b) Tony has had a positive reply from Werner Witzeling regarding the loan of some ATLAS racks to RAL, which will be followed up. 2. CMM architecture update Norman (in collaboration with Kithsiri, Sam and Uli) has produced a document discussing the issues relating to the design of a common Merger module. It seems likely that the Sum Merger module would remain as a separate design. Kithsiri is starting to look at the tools (Cadence) needed to set up a model to simulate the backplane design, looking for effects such as crosstalk, etc. A hardware demonstration may subsequently be needed if the simulation results are encouraging (necessary but not sufficient). 3. DSS system: a) Serial data connectors Bob reported that the Robinson Nugent connectors were unsuitable as they did not produce cable-mounting parts. A long discussion yielded no real conclusions - suitable connectors were either on long delivery or only available in very large minimum order quantities, or both! However, after the meeting a decision was reached to accept the long lead-time on ordering the Berg parts, as it is now probable that the DSS mother-board will be delayed. Alternative (readily-available) coaxial connectors - SMR - will be used for the G-link boards. b) DSS motherboard design status Viraj reported that Kevin has now almost completed the schematics, and he now confidently expects that they will go to the Drawing Office for layout during the week beginning 19th April. c) LVDS daughter-cards layout status Richard reported that the Receiver card layout is complete, assuming use of the Berg connectors is confirmed, and that the Transmitter card will also be similarly complete by the week beginning 19th April. d) G-link daughter-cards layout status Bob reported that the Drawing Office has almost completed component placement for both the Receiver and Transmitter cards, but again it is crucial to confirm the connector types. Tony said that he had received a request from our Heidelberg colleagues for a completion date for the Receiver card. Assuming layout completion by the week beginning 19th April, assembled Receiver cards should be available by mid-May. 4. Conference submissions Eric had circulated a request among the collaboration to ask who was intending submitting papers to the IEEE Nuclear Science Symposium or to LEB (both taking place this year in the USA). From Heidelberg there may be papers on the PreProcessor Readout Bus architecture and the MCM, and from the UK groups papers on the DSS system and ROD prototype design. Eric warned that submission deadlines for Abstracts were fast approaching! ACTION: Collate list of proposed papers - Eric. 5. ROD prototype: Norman reported that the modifications and questions thrown up by the Review were gradually getting resolved. Two current issues are the requirement from CERN that RODs are designed to the VME64 specification, and the recent realisation that the trigger-type information arrives from the TTC system very late, implying the need for buffering and queuing of many part-assembled events in the ROD, each awaiting the addition of the trigger-type. 6. CCM prototype There was some discussion about adding functionality in the CCM to provide an input for prompt trigger-type information direct from the CTP, if it were desired to read out extra time slices from the CPM serialising ASICs for calibration triggers, but it was decided to achieve this by always reading out long time frames and suppress when unwanted by post-processing in the RODs. Following discussions with several people Viraj has re-structured and simplified the specifications document, and with a few further changes it should be possible to release it on to the Web for review. Tony will circulate a note to the appropriate people when this happens. 7. Planning for system tests: a) Exploitation plan Norman has produced a draft plan describing the various stages needed to test the links using the DSS module(s), which he will put up on the Web. b) Tony noted that the timescales had unfortunately extended much further than originally anticipated, but we could now foresee the system tests taking place in June. 8. Current Review status Tony said that he will write a short summary of the outcome of each PDR, to be put up on the Web. In some cases this is not yet possible, as the specification documents have not been finalised. ACTION: Summarise outcomes of completed Reviews - Tony. 9. Any other business Norman said that ATLAS (UK) has requested that we provide by 20th April an estimate of the projected UK spend in FY1999/2000. Tony agreed to do this. * Next meeting - Tuesday 20th April at 13.30 in CR02, R1 at RAL. Tony Gillman