Quick VPT Test Rig meeting -
minutes
Date of meeting: 9 June 2000
Venue: Brunel University
Present: P Flower, H Heath, P Hobson, D Imrie, B Kennedy, L
Lintern, C Pattison, O Sharif, M Sproston, J Williams
1. Status of RAL 48-channel test rig
- ALL making VPT can for noise studies - should be ready next week.
- Reed relays have arrived
- LabView magnet control works. Current/field reading next week.
- PRH noted that the HV cables have some steel components - care must
be taken when using these in the magnetic field.
2. Status of Brunel 4T test rig
- Tour of test lab: magnet support frame is ready; magnet lab being
prepared.
- The design of the 6-channel "torpedo" is in progress.
- Need crimping tool to begin cabling up first channel; will use
correct cable lengths and read out via a 16-bit multiplexed 32-differential ADC (cost
under £1000).
- Will use McLennan stepper motor system (same as RAL) - delivery
expected by end July. This motor can be controlled using the same LabView program as
the RAL motor.
- Some discussion of data file formats. It would be advantageous
for RAL and Brunel to use compatible formats: HFH, BWK, CAXP, OOS to discuss further.
3. CRISTAL
- HFH showed examples of the process and data structure specifications required by the CRISTAL experts to set up the database.
- PRH suggested storing data from faceplate transmission measurements
in CRISTAL. At present the db is structured in terms of an heirarchy of parts and
subparts, so there is no natural way to store such information - HFH will raise the point
with CRISTAL experts.
4. Dimensioning gauge
- JHW presented a conceptual design for a gauge measuring the VPT
radius and the angle of the faceplate wrt the barrel simultaneously. Unlikely to be
ready for preproduction batch, but a fast stop/go gauge will be needed when the production
VPTs start to arrive.
5. VPT Lifetime tests
- MS reported on accelerated ageing tests on two VPTs at RAL, both
from the manufacturer chosen for the preproduction batch. Output from tube 1 is
still falling after 20 days at 200nA cathode current, now under 60% of original output.
Tube 2 has reached 78% output after 4 days, but seems to be flattening off.
6. Helium study
- PSF described preliminary work on exposure of a VPT to a helium
atmosphere. After a few days in 70% He the gain is seen to rise, and the pulse
develops a very long tail; gain/tail increase continues for at least 3 weeks.
Bruce Kennedy /
05 December 2003