Quick VPT Test Rig meeting - minutes


Date of meeting: 13 September 2002

Venue: RAL

Present: B Kennedy, L Lintern, M Sproston


  1. Status of rig: Production running - some overcurrent failures, but all failed tubes have passed a second run.
  2. Hardware: MS has tested 10 amplifier channels for row 3 using a single-channel charge-injection system.  25% variation in gain between highest & lowest.  ALL has etched PCBs for row 4.
  3. Software: JHW working on overcurrent handling.

Bruce Kennedy 05 December 2003